    GoGo Tech Proceeds with a 30-Megawatt Hydro-cooled Mining Site in Fort Worth

    'Hydro' refers to liquid (water) cooling of the miners, not hydroelectric power. Fort Worth runs on ERCOT grid power.

    Fort Worth is a 30 MW hydro-cooled site: 12 MW available now and an 18 MW second phase, sold as 2 MW MDUs. No commercial-operation month has been set.

    30MW Hydro-cooled Mining Site. In development. No commercial-operation month. Oncor constructing the power lines. Shell Energy PPA with API purchases from the ERCOT wholesale pool.

  • March 2026

    GoGo Technologies LLC Commences Operations at a Natural-Gas Mining Site in North Dakota

    Natural-gas mining site. 5 MW. North Dakota. March 2026. Over 3,000 Mcf per pad per day. Phoenix Energy; generators by Taylor Systems.

  • January 2026

    GoGo Tech Commences Mining Operations at a North Dakota Natural-Gas Site

    Natural-gas mining site. 5 MW. North Dakota. January 2026. Over 3,000 Mcf per pad per day. Phoenix Energy; generators by Taylor Systems.

  • November 2024

    GoGo Technologies LLC Commences Operations at Grid Power, an 8 MW On-Grid Mining Site in North Dakota

    8 MW on-grid mining site. North Dakota. November 2024. Local distribution service with Mountrail-Williams Electric Cooperative.